Construction Change Order Builder

Change Order Document

Header
Cost Breakdown
Type Description Amount Remove
Schedule And Contract
Subtotal $0.00
Markup $0.00
CO Total $0.00
New Contract $0.00

Self-Tests

Not run

    Change Order

    Untitled Project

    CO Number Draft
    Owner / GC -
    Date -
    Schedule Impact 0 days

    Description / Reason

    -

    Cost Breakdown

    Type Description Amount
    Subtotal $0.00
    Markup / OH&P $0.00
    Change Order Total $0.00

    Contract Math

    Original Contract $0.00
    Prior Approved COs $0.00
    This Change Order $0.00
    New Contract Total $0.00
    Contractor
    Owner
    Date

    About the Construction Change Order Builder

    Scope deviations are the leading cause of margin erosion and legal disputes in commercial construction. A construction change order builder systematically formats requests for additional work, capturing direct material, labor, and equipment costs. By automatically applying agreed-upon overhead and profit markups, the tool generates a professional document that clarifies schedule impacts and establishes a new, legally binding contract total.

    How it works

    1. Describe the change in scope and the reason for the deviation from the original contract.
    2. Itemize the estimated costs for new labor, materials, equipment, and subcontractor fees.
    3. Apply the contractually allowed percentages for overhead, profit, and tax markups.
    4. Input any required extra schedule days, review the revised contract total, and export the document for client signature.

    Frequently asked questions

    Can a contractor charge overhead and profit (O&P) on a change order?

    Yes, standard contracts dictate allowable O&P markup percentages for change orders, commonly ranging from 10% to 15% to cover administrative burdens and risk.

    What is a Construction Change Directive (CCD)?

    A CCD is issued by the owner or architect forcing the contractor to proceed with changes before a final price or time adjustment is agreed upon, usually to prevent project delays.

    Should schedule impacts be included in every change order?

    Yes. Even if a change has zero cost, if it requires additional days to complete, the contractor must explicitly claim those days on the change order to avoid future liquidated damages.

    What happens if a change order is performed without written approval?

    Proceeding with out-of-scope work without a signed change order places the financial risk entirely on the contractor. The owner may legally refuse to pay for undocumented changes.

    References