Change Order
Untitled Project
Description / Reason
-
Cost Breakdown
| Type | Description | Amount |
|---|
Contract Math
| Original Contract | $0.00 |
|---|---|
| Prior Approved COs | $0.00 |
| This Change Order | $0.00 |
| New Contract Total | $0.00 |
Change Order Document
Change Order
-
| Type | Description | Amount |
|---|
| Original Contract | $0.00 |
|---|---|
| Prior Approved COs | $0.00 |
| This Change Order | $0.00 |
| New Contract Total | $0.00 |
Scope deviations are the leading cause of margin erosion and legal disputes in commercial construction. A construction change order builder systematically formats requests for additional work, capturing direct material, labor, and equipment costs. By automatically applying agreed-upon overhead and profit markups, the tool generates a professional document that clarifies schedule impacts and establishes a new, legally binding contract total.
Yes, standard contracts dictate allowable O&P markup percentages for change orders, commonly ranging from 10% to 15% to cover administrative burdens and risk.
A CCD is issued by the owner or architect forcing the contractor to proceed with changes before a final price or time adjustment is agreed upon, usually to prevent project delays.
Yes. Even if a change has zero cost, if it requires additional days to complete, the contractor must explicitly claim those days on the change order to avoid future liquidated damages.
Proceeding with out-of-scope work without a signed change order places the financial risk entirely on the contractor. The owner may legally refuse to pay for undocumented changes.