Construction RFI Log
RFI Log Builder
| RFI # | Subject | Discipline | Status | Submitted | Due | Answered | Cost Impact | Schedule Impact | Ball-in-Court | Question | Answer | Actions |
|---|
Construction RFI Log
| RFI # | Subject | Discipline | Status | Submitted | Due | Answered | Cost Impact | Schedule Impact | Ball-in-Court | Question | Answer | Actions |
|---|
Resolving ambiguities in architectural drawings quickly is critical for maintaining construction timelines and budgets. A construction RFI log builder centrally tracks Requests for Information, highlighting schedule impacts, cost implications, and unresolved ball-in-court assignments. Proper documentation of design clarifications protects contractors from liability and forms the baseline for subsequent change order requests.
If the architect's response to an RFI alters the original scope of work, requiring more material, labor, or time, the contractor will submit a Change Order Request based on that documented RFI directive.
Standard construction contracts, such as those published by the AIA, typically allow the design team 7 to 14 days to respond to an RFI, though urgent field issues may require expedited answers.
Typically, subcontractors submit questions to the general contractor, who filters and formally submits the official RFI to the architect or engineer of record.
An RFI is considered frivolous if the answer is already clearly detailed in the contract drawings or specifications. Excessive frivolous RFIs can strain the relationship with the design team.